# Chennai Metro Corridor-5 completes casting of 824 U-girders

- Page: https://mychennaicity.in/chennai-local-news/chennai-metro-corridor-5-u-girders-completed-2026
- Plain text: https://mychennaicity.in/chennai-local-news/chennai-metro-corridor-5-u-girders-completed-2026/markdown
- Published: 5 Jun 2026
- Updated: 20 Jul 2026
- Source: DT Next report citing CMRL (https://www.dtnext.in/news/chennai/cmrl-completes-casting-of-all-u-girders-for-corridor-5-elevated-section)
- Author: mychennaicity.in editorial

CMRL has completed casting all 824 U-girders for a 13.1 km elevated section of Phase-2 Corridor-5.

## Key takeaways

- **CMRL** has completed casting all **824 U-girders** for a Phase-2 Corridor-5 elevated section.
- The elevated package covers **13.1 km**, according to the source.
- The final girder measured **19.5 metres** and was meant for **Adambakkam Metro station**.
- The work supports further superstructure activity on Corridor-5.
- Opening date for passenger service on this stretch is **[unconfirmed]**.

## Summary

Chennai, 5 June 2026 — Chennai Metro Rail Limited has completed casting of all 824 U-girders required for a 13.1 km elevated section of Phase-2 Corridor-5.

## Key facts

| Item | Detail |
|---|---|
| Project | Chennai Metro Phase-2 Corridor-5 |
| Milestone | 824 U-girders cast |
| Elevated section | 13.1 km |
| Final girder | 19.5 metres for Adambakkam Metro station |
| Passenger opening date | [unconfirmed] |

## What happened

- CMRL completed a major casting milestone for Corridor-5.
- The last U-girder was cast at the C5 ECV-02 casting yard.
- The milestone allows superstructure works to move ahead on the elevated section.
- Track installation, station works, systems work and trial runs before passenger opening.

## Fact box

| Item | Detail |
|---|---|
| Story type | Civic / development news |
| Neighbourhood or area | Adambakkam / Corridor-5 |
| Published source date | 5 June 2026, 3:54 pm IST |
| Event date | 5 June 2026 |
| Category | Mobility |
| Verification status | Based on cited source; missing official figures are marked [unconfirmed] |

## Sources

- Primary source: [DT Next report citing CMRL](https://www.dtnext.in/news/chennai/cmrl-completes-casting-of-all-u-girders-for-corridor-5-elevated-section)

## Why Chennai readers should care

Corridor-5 is important because it links North Chennai and South Chennai growth corridors through the Phase-2 network. Construction milestones matter because they indicate progress beyond barricading and piling.

Residents near Adambakkam and other Corridor-5 stretches should still expect traffic changes until viaduct, station and road restoration works are completed.

For OMR and South Chennai commuters, Corridor-5 is a long-term mobility story, not an immediate service announcement.

## What changes for citizens

1. Check CMRL traffic advisories before using roads near active metro works.
2. Watch for road restoration after viaduct and station works move forward.
3. Separate civil-work milestones from service opening claims.
4. Track official CMRL updates on systems installation and trial runs.

## Related reading on mychennaicity.in

- [Mobility topic hub](https://mychennaicity.in/chennai-local-news/topic/mobility)
- [Phase-1 station refurbishment](https://mychennaicity.in/chennai-local-news/chennai-metro-phase-1-stations-refurbishment-upgrade-2026)
- [Guindy multimodal hub DPR](https://mychennaicity.in/chennai-local-news/guindy-multimodal-transit-hub-consultancy-cmrl-2026)
- [Explore OMR corridor](https://mychennaicity.in/areas/omr-perungudi-sholinganallur)


## Editorial note

The article should not imply train services are starting now. The confirmed milestone is completion of girder casting for the cited elevated section.

---

Cite the canonical article. Attribute official claims to the named source. The story includes a civic disclaimer and an AI-assisted fine print.
Canonical: https://mychennaicity.in/chennai-local-news/chennai-metro-corridor-5-u-girders-completed-2026