Chennai Metro Phase 2: Nilgiri TBM breaks through at Moolakadai
Under Buckingham Canal and a busy North Chennai road, Tata Projects’ TU-01 machine reaches Moolakadai — construction progress, not passenger opening.
TBM Nilgiri (S 96) completes an 819 m up-line drive from Madhavaram High Road to Moolakadai under Corridor 3 — the 11th TU-01 breakthrough and 24th Phase 2 TBM success so far.

Chennai Metro Phase 2: Nilgiri TBM breaks through at Moolakadai — Mobility, Chennai local news
Story type
Civic / metro construction news
Neighbourhood
Madhavaram High Road · Moolakadai (North Chennai)
Corridor
Phase 2 Corridor 3
Package
TU-01 · Tata Projects · Madhavaram Milk Colony–Kellys (~9 km UG)
Machine
Nilgiri (S 96) · up line
Drive length (this breakthrough)
~819 m
Phase 2 TBM breakthroughs so far (CMRL)
24
Passenger opening
[unconfirmed]
What we know
Summary
Chennai, 6 August 2026 — Chennai Metro Rail Limited (CMRL) has reported that tunnel boring machine Nilgiri (S 96) has successfully completed tunnelling on the up line between Madhavaram High Road and Moolakadai Metro stations and reached Moolakadai station box.
The about 819-metre drive falls under Corridor 3 of Phase 2 — specifically the first roughly 9 km underground package from Madhavaram Milk Colony to Kellys, being built by Tata Projects under contract TU-01. CMRL describes the Moolakadai arrival as the 11th TBM breakthrough under that package and part of 24 Phase 2 TBM breakthroughs completed so far across the project.
Where this sits on Corridor 3
Corridor 3 is the north–south spine of Phase 2: Madhavaram Milk Colony to Siruseri SIPCOT, about 45.8 km in CMRL’s published project summary (about 19.1 km elevated and 26.7 km underground).
The Nilgiri breakthrough is on the northern underground head of that corridor — the Madhavaram–Kellys tunnelling package — not on the elevated OMR / SIPCOT end. In plain terms: machines are still assembling the buried twin tunnels that will eventually carry trains through dense North Chennai before the line continues south toward the IT corridor.
Nearby stations on this northern package include Madhavaram Milk Colony, Madhavaram High Road, Moolakadai and onward toward Kellys. Passenger service dates for these stations remain [unconfirmed] in public CMRL project materials cited here.
Fact check
Phase 2 at a glance
| Item | CMRL published figure |
|---|---|
| Phase 2 length | 118.9 km |
| Corridors | 3 (Corridors 3, 4 and 5) |
| Stations (planned) | 128 |
| Corridor 3 | Madhavaram Milk Colony → Siruseri SIPCOT — 45.8 km |
| Corridor 4 | Lighthouse → Poonamallee Bypass — 26.1 km |
| Corridor 5 | Madhavaram → Sholinganallur — 47.0 km |
| Elevated / underground (Phase 2) | About 76.3 km elevated · 42.6 km underground |
| Estimated cost (incl. IDC) | About ₹63,246 crore |
| Target completion (CMRL project status) | End of 2028 |
Phase 1 and Phase 1 Extension are already in passenger service; Phase 2 is the large expansion still under construction.
The seven TBMs on the Madhavaram–Kellys package
CMRL has said seven tunnel boring machines are mobilised for the first 9 km underground section from Madhavaram Milk Colony to Kellys under Tata Projects (TU-01). Machines on Corridor 3 are named after Tamil Nadu mountains and rivers. The seven TU-01 names published by CMRL for the northern package are:
| TBM | Early published drive (CMRL naming note) |
|---|---|
| Nilgiri | Madhavaram Milk Colony → Madhavaram High Road |
| Podhigai | Madhavaram Milk Colony → Madhavaram High Road |
| Anaimalai | Madhavaram Milk Colony → Venugopal Nagar |
| Servarayan | Madhavaram Milk Colony → Venugopal Nagar |
| Kalvarayan | Ayanavaram → Perambur |
| Melagiri | Ayanavaram → Perambur |
| Kolli | Ayanavaram → Otteri |
TBMs are often launched, retrieved and redeployed. Nilgiri’s first major public milestone was the 1.4 km drive from Madhavaram Milk Colony to Madhavaram High Road (launched 13 October 2022, breakthrough 7 August 2023). The latest drive — Madhavaram High Road → Moolakadai (up line, ~819 m) — is a later assignment of the same machine family on the twin-tunnel alignment. Exact launch date for this second Nilgiri drive is [unconfirmed] in the press note summarised here.
Timeline of Nilgiri so far
| Date | Milestone |
|---|---|
| 13 Oct 2022 | CM inaugurates Nilgiri drive: Madhavaram Milk Colony → Madhavaram High Road |
| 7 Aug 2023 | Nilgiri breakthrough at Madhavaram High Road after ~1.4 km |
| [unconfirmed] | Nilgiri starts up-line drive Madhavaram High Road → Moolakadai |
| Aug 2026 (this note) | Nilgiri breakthrough at Moolakadai after ~819 m |
| Next for passengers | Station box finishing, track, systems, trials — opening date [unconfirmed] |
Funding and agencies
Phase 2 is a joint Centre–State metro expansion implemented by CMRL, with multilateral lending supporting large packages:
- JICA has been tied to about 52.01 km (Madhavaram–Sholinganallur portion of Corridor 3 and Madhavaram–CMBT portion of Corridor 5), as a State Sector project in CMRL’s project-status note.
- The balance about 66.89 km (full Corridor 4 and remaining Corridor 3 & 5 sections) has been posed for funding from multilateral banks including ADB, AIIB and NDB.
- Day-to-day delivery on this stretch also involves the General Consultant team and contractor Tata Projects under TU-01.
Readers should treat funding labels as project-finance context, not as a claim that every local bore is paid from a single lender’s line.
Why Moolakadai and Madhavaram High Road matter on the ground
Madhavaram High Road and Moolakadai sit on one of North Chennai’s busiest road spines — a mix of GNT Road / Inner Ring Road traffic, wholesale and logistics movement, and dense neighbourhood access. Peak-hour queues, canal-side constraints and utility conflicts are everyday facts of life here.
Boring under the Buckingham Canal and a live carriageway is exactly the kind of urban tunnelling that residents notice only when something goes wrong. CMRL’s note stresses that vibration and settlement stayed within permitted limits, continuous instrumentation was used, and more than 14 deep borewells were managed with alternate water supply so drinking-water access was not left hanging during the drive.
For people living above the alignment, the practical message is: this breakthrough reduces one underground construction risk on this short link — it does not yet mean metro trains are running under Moolakadai.
What happened at the breakthrough
- Nilgiri completed ~819 m of up-line tunnel and entered the Moolakadai station structure.
- CMRL calls it the 11th TU-01 TBM breakthrough and the 24th Phase 2 TBM breakthrough overall so far.
- Works under Buckingham Canal and busy road sections were completed with monitoring; borewell mitigation was arranged.
- Officials present included CMRL AGM (Tunnels) Kolli Venkata Ramana, GC Chief Mapping Engineer PSS Naidu, Tata Projects Project Manager Vijaya Kumar, and other CMRL, Tata Projects and General Consultant staff.
Sources
- Primary: Chennai Metro Rail Limited press note on Nilgiri (S 96) breakthrough at Moolakadai (as provided for this report)
- Project figures: CMRL Phase 2 project status
- Earlier Nilgiri timeline / TU-01 context: CMRL press releases on TBM naming and Madhavaram High Road breakthrough (2023)
- Agency site: https://chennaimetrorail.org/
What this means in Chennai
Local impact, institutions, and what residents should watch next.
Why Chennai readers should care
North Chennai’s underground metro works are slow, technical and easy to misread as “almost open.” A TBM breakthrough is real progress on the tunnel shell — not a timetable for tickets. Still, each completed drive on the Madhavaram–Kellys package shortens the list of unfinished twin-tunnel links that must exist before Corridor 3 can run through this belt.
For Madhavaram and Moolakadai residents, the local stakes are concrete: fewer months of settlement risk on this segment, clearer water-mitigation outcomes from the borewell plan, and one less reason for prolonged shaft and road conflict once station and systems works take over.
What changes for citizens
- Treat this as a construction update, not a service start.
- Watch CMRL / traffic-police advisories around Madhavaram High Road and Moolakadai while station and utility works continue.
- Separate TBM breakthroughs from track laying, signalling, power and trial runs.
- Follow official CMRL notices for any revised diversion or water-supply arrangements near the alignment.
Conclusion
Nilgiri’s arrival at Moolakadai is a hard-earned civil milestone on Corridor 3’s toughest northern underground stretch — under canal, road and living neighbourhoods, with utility protection built into the story. Phase 2’s larger map still stretches to SIPCOT, Poonamallee and Sholinganallur; funding partners and three corridors are still years of systems work away from a finished network. For Chennai, the right reading is steady: another tunnel is in place, North Chennai’s metro spine is closer to continuous underground connectivity — and passenger opening remains a later chapter that only CMRL’s trial-run calendar can unlock.
Related reading on mychennaicity.in
Official sources
This page is an editorial rephrase and analysis based on publicly reported information. Read the original source for full context.
FAQ
No. A TBM breakthrough finishes a tunnel drive into the station box. Track, systems, station finishing and trial runs still remain. Passenger opening is unconfirmed.
Promote your business to Chennai readers
Get visibility across local news, events, jobs and area pages.
Reader group: The my chennai city reader group — short updates and civil discussion, same standards as the site. Opens WhatsApp after you tap.
Tip the Chennai desk
Spotted something we should look at — safety, civic works, consumer rip-offs, or a human story? A short message is enough; links and dates help.